Bishopsgate Tunnel

London, United Kingdom · 1964

Bishopsgate Tunnel — intermediate deck strengthening
Problem

The deck of the former rail goods yard needed additional structural capacity for public use.

CINTEC solution

Anchoring and strengthening works were introduced to support the grillage of girders and jack arches.

Technical notes

The intervention was designed for redevelopment constraints without dismantling the historic deck structure.

Result

The deck was strengthened and prepared for adaptive reuse.